The 2027 datacenter boom is already being built and next week’s midterms won’t stop it now. Roughly three-quarters of the 33.8 GW due across our top 20 states is already under construction, which is why we remain comfortable with the global +50 GW year we laid out in our Oct. 16 article. The campuses are taking shape. The election will change the rules around them, but much of the 2027 pipeline already has a substantial head start.

2027年的数据中心繁荣期正在建设中,下周的中期选举已无法阻止这一进程。在我们排名前20的州中,预计新增的33.8 GW容量已有约四分之三处于在建状态,这也是为什么我们对我们10月16日文章中提出的全球+50 GW年度目标保持乐观的原因。这些园区正在成型。选举将改变围绕它们的规则,但2027年管道中的大部分项目已经取得了显著的领先优势。

The fight is over 2028. Our model has 62.2 GW of US net additions that year, most of which hasn’t started construction. Most of it sits in states electing a governor on Nov. 3. This piece tracks the 13 states with the largest 2028 net additions in our model, setting aside Virginia and Mississippi, which don’t hold state elections this November. Together they account for 43.5 GW, or 70% of what we expect nationally, and 10 of the 13 elect a governor.

争夺的焦点是2028年。我们的模型显示,美国当年净增容量为62.2 GW,其中大部分尚未开始建设。大部分项目位于11月3日进行州长选举的州。本文追踪了我们模型中2028年净增容量最大的13个州,排除了弗吉尼亚州和密西西比州,因为它们今年11月不举行州选举。这13个州合计占43.5 GW,约占我们全国预期总量的70%,其中13个州中有10个州进行州长选举。

Source: SemiAnalysis Datacenter Industry Model

来源:SemiAnalysis数据中心行业模型

That leaves a 2028 pipeline still working through approvals, power projects and construction schedules as the rules change. In September, we argued that datacenter moratoriums weren’t killing the US buildout: of roughly 20 GW inside local restrictions, we estimated only 1.5 GW faced delay. Most exposed capacity already had protections or did not need the affected approval until after the pause expired. That broad conclusion has held up. What is changing is the reach of the restrictions given the growing anti-datacenter backlash.

这意味着2028年的管道仍在审批、电力项目和施工计划中推进,同时规则也在变化。9月份,我们认为数据中心的暂停令并没有扼杀美国的建设扩张:在地方限制范围内的约20 GW容量中,我们估计只有1.5 GW面临延迟。大多数受影响的容量要么已经受到保护,要么不需要在暂停期结束前获得相关批准。这一广泛结论依然成立。发生变化的是随着反数据中心情绪日益高涨,限制措施的范围也在扩大。

Three things have worsened since. Texas, the largest US market, froze Texas Commission on Environmental Quality (TCEQ) permits on Sept. 21 on top of the interconnection-queue audit begun Aug. 3, bringing onsite power into the hold. Oregon expanded its earlier state-land freeze to air and water-discharge permits on Oct. 9, through July 1, 2027. And midterm candidates have campaigned on more restrictive positions: nine of the 20 nominees want a pause on new construction and the other 11 want conditions, and the split is about even by party. Both parties want developers to accept stricter conditions. The main difference is whether a developer can meet the new terms and keep building, or has to wait for the state to reopen approvals.

此后情况恶化了三个方面。作为美国最大市场的德克萨斯州,于9月21日冻结了德克萨斯州环境质量委员会(TCEQ)的许可,加上8月3日开始进行的并网队列审计,使得现场电力供应也被纳入冻结范围。俄勒冈州将其此前对州立土地的冻结扩展到空气和水排放许可,有效期至2027年7月1日。中期选举候选人采取了更严格的立场进行竞选:20名候选人中有9人希望暂停新项目建设,另外11人则要求附加条件,两党在此问题上平分秋色。两党都要求开发商接受更严格的条件。主要区别在于开发商能否满足新条款并继续建设,还是必须等待州政府重新开放审批。

The biggest risk to our buildout forecast right now is a prolonged permitting freeze at the TCEQ. Texas alone adds close to 30% of US GW in 2028. A few months of lost time in that market can move the national number. We already flagged to Datacenter Model subscribers which companies are most at risk from the current pause. The question now is how long the pause lasts.

目前对我们的建设预测最大的风险是德克萨斯州环境质量委员会(TCEQ)的许可冻结长期持续。仅德克萨斯州在2028年就将增加近30%的美国GW产能。该市场几个月的时间损失可能会影响全国数字。我们已向数据中心模型订阅者指出,哪些公司最有可能受到当前暂停的影响。现在的问题是暂停会持续多久。

Gov. Greg Abbott (R), who is running for re-election in Texas, could reopen permitting once the Electric Reliability Council of Texas (ERCOT), the state’s grid operator, finishes its audit and the Texas Water Development Board completes its water-use review. ERCOT is targeting Dec. 10 to file its report, which does not by itself reopen permitting. A restart around then would leave developers dealing with a relatively short interruption, which some projects can absorb within their schedules. The audit still has to lead to a decision to resume issuance, and each permit still needs approval.

正在竞选连任的德克萨斯州州长格雷格·阿博特(Greg Abbott,共和党人)可能在德克萨斯电力可靠性委员会(ERCOT,该州的电网运营商)完成审计以及德克萨斯州水资源开发局完成用水审查后重新开放许可。ERCOT的目标是在12月10日提交报告,但这本身并不会重新开放许可。如果在那时重启,开发商将面临相对短暂的中断,一些项目可以在其计划内吸收这种中断。审计仍需导致恢复颁发的决定,且每个许可证仍需获得批准。

By contrast, Gina Hinojosa (D), his challenger, presents a more bearish approach: She would impose a moratorium until legislation is passed that gives communities a voice and protects household utility bills, as well as ends the tax incentives for datacenters. The regular legislative session in Texas takes place from Jan. 12 to May 31, 2027. By keeping approvals on hold throughout that session, the freeze would last about eight months from September. If you wait for the new rules to come into effect in late summer, it will be close to a year, that is five to nine additional months compared to restarting in December. A deal or a special session might happen sooner. However, a campus racing toward delivery in 2027 may not have that much time to spare.

相比之下,他的挑战者吉娜·希诺霍萨(Gina Hinojosa,民主党人)提出了更为悲观的方法:她将实施禁令,直到通过赋予社区发言权、保护家庭公用事业账单以及结束数据中心税收激励措施的立法。德克萨斯州的常规立法会议将于2027年1月12日至5月31日举行。如果在整个会议期间保持审批暂停,冻结将从9月开始持续约八个月。如果你等到新规则在夏末生效,那将接近一年,即比12月重启多出五到九个月。可能会提前达成交易或召开特别会议。然而,一个计划在2027年交付的数据中心园区可能没有那么多宽裕的时间。

Source: SemiAnalysis Datacenter Industry Model

来源:SemiAnalysis数据中心行业模型

This is the risk posed by the pro-moratorium candidates: a project cannot carry out work if it still requires an approval which the state has ceased to issue. If the candidate proposing a datacenter pause won in every state where one is running, those states would together contain roughly 30 GW of planned capacity scheduled for 2028. How much actually slips depends on the permits each project still needs and how long the pause lasts.

这是支持暂停候选人的风险:如果一个项目仍需要州政府停止颁发的批准,它就无法开展工作。如果提议暂停数据中心的候选人在所有有候选人参选的州都获胜,这些州将总共包含约30GW的规划产能,安排在2028年。实际延误多少取决于每个项目仍需要的许可证以及暂停持续的时间。

Source: SemiAnalysis Datacenter Industry Model

来源:SemiAnalysis数据中心行业模型

We are less concerned with the candidates who support conditions only. Most of their demands change the price and terms of development. A developer can fund the grid upgrade, change the cooling design or negotiate the community agreement and then move forward. That can be expensive and time-consuming, but it gives projects a route to approval. Several of the main conditions were already coming:

我们不太担心那些仅支持附加条件的候选人。他们的大多数要求会改变开发的价格和条款。开发商可以资助电网升级、更改冷却设计或协商社区协议,然后继续推进。这可能既昂贵又耗时,但为项目提供了一条获批的途径。其中几项主要条件已经出现:

  • Submitting thorough water-usage studies: manageable for many projects, but the answer depends on cooling design and the local water supply.
  • Paying the infrastructure costs they create: We expect this to come anyway, with datacenter developers now offering credits toward household electricity bills
  • More environmental transparency and dropping non-disclosure agreements (NDAs) – Amazon Web Services (AWS) and Google have already started down this path
  • 提交详尽的用水研究:对许多项目来说是可以管理的,但答案取决于冷却设计和当地供水情况。
  • 支付他们造成的基础设施成本:我们预计这无论如何都会发生,数据中心开发商现在正提出向家庭电费账单提供抵免额
  • 更高的环境透明度并放弃保密协议(NDAs)——亚马逊网络服务(AWS)和谷歌已经在这条道路上开始行动

If the less restrictive candidates win, that exposure falls to 5.7 GW, mainly because Ohio and Oregon have proponents of a pause on both sides. That is a much smaller pipeline to test for delays. It would still be a tougher development environment: fewer tax breaks, more upfront commitments and less room to leave infrastructure costs with the utility’s other customers.

如果限制较少的候选人获胜,这种暴露量将降至5.7 GW,主要是因为俄亥俄州和俄勒冈州在暂停问题上双方都有支持者。这是一个规模小得多的管道,用于测试延误。它仍然是一个更艰难的开发环境:税收优惠更少、前期承诺更多,以及将基础设施成本留给公用事业公司其他客户的空间更小。

Source: SemiAnalysis Datacenter Industry Model

来源:SemiAnalysis 数据中心行业模型

According to race ratings and available polling as of Oct. 30, from multiple sources (Cook Political Report, Multistate, and The New York Times), the conditions-only candidate is favored in Texas, Oklahoma, Pennsylvania, and Iowa, and Georgia is a toss-up. Here we take candidates’ positions at face value. It will be up to whether these promises are turned into actual policy and whether the resulting pause intervenes in a project at the wrong stage in its timeline to determine the extent of the delay.

根据截至10月30日的选情评级和可用民调数据,来自多个来源(Cook Political Report、Multistate 和《纽约时报》),仅支持附加条件的候选人在德克萨斯州、俄克拉荷马州、宾夕法尼亚州和爱荷华州占优,而佐治亚州则是势均力敌。在这里,我们按字面意思理解候选人的立场。最终延误的程度将取决于这些承诺是否转化为实际政策,以及由此产生的暂停是否在项目时间线的错误阶段介入。

Source: SemiAnalysis Datacenter Industry Model

来源:SemiAnalysis 数据中心行业模型

As noted in our September moratoriums article, these positions are overwhelmingly bipartisan now, with many campaigning on the following three points:

正如我们在9月的暂停文章中指出的那样,这些立场现在是压倒性的两党共识,许多人围绕以下三点进行竞选:

  • Make datacenters pay their own grid costs (15 candidates)
  • End the tax breaks (12 candidates)
  • Limit or report water use (11 candidates).
  • 让数据中心承担自己的电网成本(15名候选人)
  • 取消税收优惠(12名候选人)
  • 限制或报告用水量(11名候选人)。

Source: SemiAnalysis Datacenter Industry Model

来源:SemiAnalysis 数据中心行业模型

Which states are the most impacted depends on which companies are building. We interviewed six current and former employees of hyperscalers, including people who worked at Amazon, Microsoft and Google and are involved in datacenter development. Several said that hyperscalers can afford to pay the higher costs of new rules and can more easily bring or pay for their own power.

哪些州受到的影响最大,取决于哪些公司正在建设。我们采访了六名来自超大规模云服务商的现任和前任员工,包括曾在亚马逊、微软和谷歌工作并参与数据中心开发的人员。其中几人表示,超大规模云服务商能够承担新规带来的更高成本,并且更容易自行获取或支付电力费用。

However, that doesn’t necessarily mean they will be able to deliver capacity on time. These projects still require their own permits and equipment. And having the money to pay for power transmission doesn’t make it available immediately. A moratorium can block any project that still needs approval, and it won’t be easy to shift development to another state: anywhere else would still require power, permits and construction schedules that can meet the same delivery timeline.

然而,这并不一定意味着他们能够按时交付容量。这些项目仍需获得各自的许可和设备。拥有支付电力传输费用的资金并不意味着电力可以立即投入使用。暂停令可能会阻碍任何仍需批准的项目,而将开发转移到其他州也并非易事:其他地区仍然需要满足相同交付时间表的电力、许可和建设进度。