Oracle Stargate项目因管道审批受阻,发不可抗力通知延期付租

Oracle's $500 Billion AI Bet Is BREAKING

原文
发到 X
推荐理由

揭示了AI算力热潮背后的基础设施瓶颈与债务风险,Oracle发出的不可抗力通知是实质性的合同违约风险信号,直接影响投资者对该公司现金流及信用评级的判断,建议关注其财报披露的债务细节。

One of America's biggest AI bets is running into serious trouble. The [music] Stargate Data Center in New Mexico is supposed to help power OpenAI and become one of the foundations of America's AI boom. But before it's even finished, Oracle is already preparing for delays. And the problem isn't chips, computing power, or AI models. It's a gas [music] pipeline. The pipeline meant to feed the incredibly energy hungry site is stuck in regulatory delays, putting the whole thing in jeopardy.

美国最大的 AI 赌注之一正陷入严重困境。位于新墨西哥州的 [音乐] Stargate 数据中心本应为 OpenAI 提供动力,并成为美国 AI 繁荣的基石之一。但该项目尚未完工,甲骨文(Oracle)就已经开始为延期做准备。问题不在于芯片、算力或 AI 模型,而是一条天然气管道 [音乐] 。这条旨在为这个极度耗能站点供气的管道因监管延误而停滞,使整个项目面临风险。

And in late September, Oracle saw the writing on the wall and moved to protect [music] itself, securing the right to hold back the rent it's supposed to be paying if the site isn't ready on time. And this is where the problem begins. Because Stargate isn't just another data center. It's at the heart of an AI infrastructure boom being built with ungodly amounts of borrowed money. Loans are piling up. Investors are betting on relentless AI demand, and these projects need to be built, filled, and generating cash on schedule.

9 月下旬,甲骨文见势不妙,采取行动保护 [音乐] 自身利益,获得了在站点未能按时就绪时扣留应付租金的权利。而这正是问题的开端。因为 Stargate 不仅仅是一个普通的数据中心。它处于一场 AI 基础设施繁荣的核心,这场繁荣正由天文数字般的借贷资金推动建设。贷款堆积如山,投资者押注于持续强劲的 AI 需求,而这些项目必须按计划建成、填满并产生现金流。

If that starts going wrong, which it is, the debt doesn't just disappear. Things get nasty very [music] fast. So, in this video, we're going to look at the money behind Stargate. From one delay pipeline in New Mexico to the mountain of debt holding up America's AI boom. My name is DC [music] and this is the Coin Bureau. Okay, so what exactly was Stargate supposed to be? Well, it was unvealed at the White House in January 2025 with OpenAI, Oracle, and SoftBank as the partners and MGX named alongside them.

如果这一切开始出错——事实确实如此——债务并不会凭空消失。局面会迅速变得非常 [音乐] 棘手。因此,在本视频中,我们将审视 Stargate 背后的资金流向。从新墨西哥州的一条延误管道,到支撑美国 AI 繁荣的巨额债务山。我是 DC [音乐] ,这里是 Coin Bureau。那么,Stargate 原本究竟打算做什么呢?它于 2025 年 1 月在白宫揭幕,合作伙伴包括 OpenAI、甲骨文和软银,MGX 也一同亮相。

The headline figure was up to $500 billion of AI infrastructure built on American soil. Oracle would build and run the data centers and OpenAI would be the customer filling them. And in September last year, that setup was officially priced. A $300 billion 5-year contract between the two set to kick in properly in 2027. The promise was absolutely huge, and the timeline was even faster. And the New Mexico site was where all of it was supposed to become a reality.

headline 数据是将在美国本土建造高达 5000 亿美元的 AI 基础设施。甲骨文将负责建设和运营数据中心,而 OpenAI 将是填充这些设施的租户。去年 9 月,这一安排正式确定了价格。双方签订了一份为期 5 年、价值 3000 亿美元的合同,预计将于 2027 年正式生效。承诺极其宏大,时间表甚至更快。而新墨西哥州的站点正是这一切变为现实的地方。

It's called Project Jupiter, a campus of about 1,400 acres in Santa Teresa, Dona Anna County, right by the US Mexico border. The developers are Stack Infrastructure and Borderlex Digital Assets, both tied to the notorious Blue Owl Capital. Oracle is the anchor tenant and the capacity serves OpenAI and the ambition only grew. The site was originally discussed at about 1 GW, but that was pushed as high as 2.45 GW. Now, the important thing about data centers is this.

该项目被称为“朱比特计划”(Project Jupiter),位于圣特雷莎(Santa Teresa),多尼亚安娜县(Dona Anna County),紧邻美墨边境,占地约 1400 英亩。开发商是 Stack Infrastructure 和 Borderlex Digital Assets,两者均与臭名昭著的蓝 owl 资本(Blue Owl Capital)有关联。甲骨文是主力租户,容量服务于 OpenAI,且野心不断膨胀。该站点的规模最初讨论约为 1 GW,但后来被推高至 2.45 GW。现在,关于数据中心重要的是这一点。

They're only as good as the power running into them. You can fill a building with the most advanced chips on the planet, but without electricity, you've just built a very, very expensive shed. Now, with that image in mind, remember Jupiter was supposed to be the project that proved Stargate could actually work. Get gigawatts of AI compute running in the desert by 2028, and the $500 billion vision becomes a reality. But if you miss that, it doesn't.

它们的性能完全取决于输入功率。你可以用全球最先进的芯片填满一栋建筑,但如果没有电力,你只是建了一座非常、非常昂贵的棚屋。带着这个画面,请记住:木星项目原本是用来证明星际之门(Stargate)真正可行的计划。到2028年要在沙漠中运行吉瓦级(gigawatts)的AI算力,5000亿美元愿景才能成为现实。但如果错过了那个节点,它就无法实现。

So, where does all of that power actually come from? Well, not from the grid. No local grid can supply a load that size. So, the site has to make its own. Back in April, the developers dropped their gas turbine plans and switched to an off-grid micro grid of Bloom Energy fuel cells running on natural gas and built right on site. But fuel cells need fuel, and that fuel needs a pipe. Enter the Green Chile project, a 17-m gas pipeline developed by Energy Transfer.

那么,所有这些电力究竟来自哪里?好吧,不是来自电网。没有任何本地电网能够供应如此庞大的负荷。因此,该站点必须自产电力。早在四月,开发商放弃了燃气轮机计划,转而采用基于天然气运行的Bloom Energy燃料电池离网微电网,并直接在现场建设。但燃料电池需要燃料,而燃料需要管道。于是出现了Green Chile项目,这是由Energy Transfer开发的一条17英里长的天然气管道。

And that's where things started to go wrong. In March, New Mexico's state land office denied the pipeline rights of way across state trust land. The developers asked it to reconsider. So in July, it said no. Again, the Federal Bureau of Land Management approved a segment on emergency review in May, but the state's refusal still forced a reroute. This pushed the pipelines in service date from August this year to February 2027.

事情就是从那里开始出错的。三月,新墨西哥州土地办公室拒绝了该管道穿越州信托土地的通行权。开发商请求重新考虑。因此七月,对方再次拒绝。尽管联邦土地管理局在五月通过紧急审查批准了其中一段,但州的拒绝仍迫使路线重新规划。这导致管道的投入使用日期从今年的八月推迟到了2027年二月。

Meanwhile, the air permit for the fuel cells is still waiting on New Mexico's environment department, and environmental groups have obviously taken the project to court. Land rights, air permits, lawsuits, each one its own separate fight, which brings us to the official notice issued by Oracle known as Fox Majour. Force majour is a legal notice saying events outside your control are getting in the way of a contract. Now, Oracle sent it to Blue Owl stack infrastructure unit and seeks the right to defer lease payments by up to 3 years if the site misses its 2028 target.

与此同时,燃料电池的空气许可仍在等待新墨西哥州环境部门的审批,环保组织显然已将该项目诉诸法庭。土地权利、空气许可、诉讼,每一项都是独立的斗争,这就引出了Oracle发布的正式通知,名为“Fox Majour”。Force majeure(不可抗力)是一份法律通知,声明超出你控制范围的事件正在阻碍合同履行。现在,Oracle已将其发送给Blue Owl Stack基础设施部门,如果站点未能达成2028年的目标,则寻求最多延期3年支付租金的权利。

So, in essence, it's Oracle saying there's a decent chance we won't pay rent if this doesn't change. And at the time it was sent the fuel cell micro grid was only about 10% built. So, the most hyped AI project in America isn't being held up by a shortage of GPUs or a rival lab. It's paperwork and a pipe that are blocking the way. And that's the part of the entire AI trade that tends to be overlooked. Software scales at the push of a button.

因此,本质上,这是Oracle在说:如果情况不改变,我们很可能不会支付租金。而在发出该通知时,燃料电池微电网的建设进度仅约为10%。所以,美国最受瞩目的AI项目并非被GPU短缺或竞争对手实验室所阻碍。而是文书工作和一条管道挡住了去路。而这正是整个AI行业中往往被忽视的部分。软件只需按下按钮即可扩展规模。

Easy peasy. But power and permits, they don't scale that way. They take time, sometimes a lot of time. Now, believe it or not, the pipeline is only one part of this mess. There are also issues with the money involved here, and we'll get to that in just a moment. But first, keeping up with the AI money trail and the policy moves behind it is next to impossible for one person. So, the good news is that our research team is ready to do it for you through the Coin Bureau Club live plan right here on YouTube.

小菜一碟。但电力和许可审批,并不会以这种方式快速扩展。它们需要时间,有时是非常长的时间。现在,信不信由你,管道只是这一团乱麻的一部分。这里还涉及资金问题,我们稍后会谈到。但首先,对于个人来说,紧跟AI的资金流向及其背后的政策动向几乎是不可能的。所以,好消息是,我们的研究团队已经准备好通过YouTube上的Coin Bureau Club直播计划为你完成这项工作。

This is where you get daily coverage across all manner of markets. Our team's read on where capital is flowing next and none of the usual financial media nonsense. And the best part, if you join today, your first month is absolutely free. Just tap the join button below this video to get started. Okay, back to Oracle. So, who's actually paying for all of this? Well, let's begin with the site. Project Jupiter runs on borrowed money.

在这里,你可以获得对所有类型市场的每日报道。我们的团队对资本下一步流向的解读,没有那些常规金融媒体的废话。而且最棒的是,如果你今天加入,第一个月完全免费。只需点击本视频下方的“加入”按钮即可开始。好了,回到甲骨文(Oracle)。那么,到底是谁在为这一切买单呢?好吧,让我们从项目所在地开始。木星(Jupiter)项目依靠借来的资金运行。

Blue Owl put in about $3 billion of equity and a bank group arranged 18 billion in construction loans with lenders such as Goldman Sachs, Sentenna, and Jeff. Then there's Oracle. To build capacity for OpenAI, Oracle spending has more than tripled in a single year. In the quarter that ended in August, it spent $28.5 billion on capital expenditure, up from 8.5 billion just a year earlier. That left free cash flow in the red and total debt sitting at $156 billion.

蓝鸟资本(Blue Owl)投入了约30亿美元的股权,一家银行集团安排了180亿美元的建设贷款,贷款方包括高盛、Sentenna和Jeff。然后是甲骨文(Oracle)。为了为OpenAI建设产能,甲骨文的支出在一年内翻了三倍多。在截至八月的季度中,其资本支出为285亿美元,而一年前仅为85亿美元。这导致自由现金流陷入赤字,总债务高达1560亿美元。

And management signaled about $40 billion more in debt and equity raising this fiscal year. Then we have the customer. Open AAI is the one meant to pay Oracle, but OpenAI funds itself largely with investor money and it's currently eyeing a fresh $30 billion private round. So, here's what we're looking at. Banks lend to the developer. Oracle borrows to build. Open AAI raises money to pay Oracle. And the whole structure relies on absolutely everyone else's cash arriving on schedule.

管理层表示,在本财年还将额外筹集约400亿美元的债务和股权融资。然后我们有客户。OpenAI本应向甲骨文付款,但OpenAI主要依靠投资者资金运作,目前正瞄准新一轮300亿美元的私募融资。所以,我们看到的情况是这样的:银行向开发商提供贷款;甲骨文借款进行建设;OpenAI筹集资金来支付给甲骨文。整个结构依赖于其他所有人的资金按时到位。

One delay anywhere hits every single link. And that's why New Mexico is such a big deal. A site that isn't running obviously doesn't earn a penny, but the interest on the loans keeps ticking every single day. That's what the forks majour notice really does. If Oracle can deposits rents, the cost of the delay doesn't go away. It just gets pushed down the chain onto the lenders and the equity holders and the lenders are not oblivious to this.

任何一环的延误都会影响每一个环节。这就是为什么新墨西哥州如此重要。一个没有运行的站点显然赚不到一分钱,但贷款的利息每天都在累积。这正是福克马乔尔(Forks Majour)通知所揭示的现实。如果甲骨文无法支付租金,延误的成本并不会消失。它只是被推向了链条下游,转嫁给贷款人和股权持有人,而贷款人对此并非毫无察觉。

Those construction loans have been trading at 89 cents on the dollar and the banks behind them can't offload them. Oracle's credit is also reflecting all of this. S&P cut Oracle to tripleB in July, a single notch above junk. And the cost of ensuring Oracle's debt against default hit a record in late September. Now, that's not the kind of record to be proud of. But the company's debt is only one element here. The man who founded it has a borrowing problem of his own.

这些建筑贷款一直以面值的89美分交易,背后的银行无法将其脱手。Oracle的信用状况也反映了这一切。标准普尔在7月将Oracle的评级降至BBB级,仅比垃圾债高一个等级。而在9月下旬,为Oracle债务提供违约保障的成本创下历史新高。当然,这并不是什么值得骄傲的记录。但公司的债务只是其中一部分。这位创始人自己也面临着借贷问题。

Larry Ellison has pledged a huge part of his Oracle shares as collateral for personal loans. According to Oracle's latest proxy filing, that's around 430 million shares, more than a third of his holdings and 19% more than just a year earlier. A pledge works a bit like a mortgage, except the house is Oracle stock. So, if the share price

拉里·埃里森已将其持有的大部分Oracle股票作为个人贷款的抵押品。根据Oracle最新的委托书申报文件,这涉及约4.3亿股,占其持股总额的三分之一以上,比一年前多出19%。质押运作方式有点像抵押贷款,只不过这里的“房子”是Oracle的股票。因此,如果股价